Looking Back at Where We Started

Bachmann Construction has continued framing the 2nd + 3rd Floor and now each floor has an open concept!

3rd Floor- Current

2nd Floor- Current

As we look at our most recent changes it is exciting to look back at how far 210-212 West Fulton Street has come! Let’s view the videos below starting with our first walkthrough video of the 2nd and 3rd floor taken March 3, 2024. . .

… compared to the progress the Bachmann Crew has completed with our 2nd & 3rd-floor walkthroughs taken July 9, 2024.

The biggest obstacle Bachmann Construction faced was the issues with the structural security of the building. After many structural surprises, 210 West Fulton Street can stand on its own with only post-shores remaining!