October 3, 2024

🙏Thank you to WMTV 15 News for covering our current ongoing project the 210 West Fulton Street Project! The 210 Project still needs your HELP and you can HELP today! Please contact Sarah Williams at 608.921.2905 or outreachwilliams@gmail.com to learn more about the project. This amazing old building needed additional support work; not uncommon in …Read More




Dock/Donation Hours

September 19, 2023

ECO Thrift Store takes a wide variety of donations! Most donations can be dropped off on our donation dock anytime during the following hours! Some donations, such as furniture, will need to be examined and approved before we will accept them! If you have any questions about your donations please contact us @ 608.884.9593 DonationHoursMonday10am-4:30pmTuesday10am-5:30pmWednesday10am-5:30pmThursday10am-4:30pmFriday10am-4:30pmSaturday10am-2:30pm …Read More


In Store Sales & Online Store

June 14, 2023

In Store Sales Edgerton Outreach Thrift Store is located at 106 S. Main St Edgerton, WI 53534. If you have any questions regarding the Sales or Items for Sale contact us at 608-884-9593 Online Store PLEASE NOTE: All pieces are sold as is. Any items listed as *Consignment* has set prices. If you are interested …Read More


Framing Apartment Layouts & Brand New Stairs

September 5, 2024

210 West Fulton Street is getting closer to completion. Bachmann Construction has finished framing the layout for the 2nd-floor apartments and continues framing the 3rd-floor and brand-new staircases. The Bachmann crew has completed framing the layout for the 2nd-floor apartments, and . . . . . . continue framing the 3rd-floor layout and the brand-new …Read More


Drywall, Framing, and Concrete

August 9, 2024

Bachmann Construction is continuing with framing the back attachment, laying drywall on the 3rd floor, (2nd floor ceiling), and pouring the concrete over the 1st floor dirt pit. The Bachmann crew has laid out the floor plan on the 2nd and 3rd floors and has begun laying drywall! Before pouring concrete, we have BEFORE pictures …Read More


Looking Back at Where We Started

July 22, 2024

Bachmann Construction has continued framing the 2nd + 3rd Floor and now each floor has an open concept! 3rd Floor- Current 2nd Floor- Current As we look at our most recent changes it is exciting to look back at how far 210-212 West Fulton Street has come! Let’s view the videos below starting with our …Read More


Structural Framing of the 2nd and 3rd Floors

July 3, 2024

Demolition of the 2nd and 3rd floors is complete and 90% of the shoring has been removed as Bachmann Construction continues the structural framing on both floors. Though this weeks update is short, it is also very exciting to see the immense changes from what the 2 floors looked like during our last update! The …Read More


Firewalls, Structural Security, and Build Ups

June 14, 2024

Lindell Masonry has completed the firewall and Bachmann Construction continues to work on structurally securing the building and building the 2nd & 3rd floors back up. The firewall is now complete and with that Lindell Masonry is finished with 210 West Fulton Street for now! Thank you to the Lindell crew for your excellent work. …Read More


2nd & 3rd Floor Progression (Videos)

June 8, 2024

The 210 West Fulton Street Veteran’s Housing Project, when complete, will be an exciting addition to Edgerton, WI. Are you curious about the work that has been completed so far? Edgerton Community Outreach (ECO) has out together 2 videos of the progress that has been completed on the 2nd and 3rd floors of the building! …Read More