Click some pictures to be directed to websites and articles. Scroll down to read MORE Outreach News

Click to Register or to Become a Sponsor!
Click for more information!

Looking Back at Where We Started

July 22, 2024

Bachmann Construction has continued framing the 2nd + 3rd Floor and now each floor has an open concept! 3rd Floor- Current 2nd Floor- Current As we look at our most recent changes it is exciting to look back at how far 210-212 West Fulton Street has come! Let’s view the videos below starting with our …Read More


Structural Framing of the 2nd and 3rd Floors

July 3, 2024

Demolition of the 2nd and 3rd floors is complete and 90% of the shoring has been removed as Bachmann Construction continues the structural framing on both floors. Though this weeks update is short, it is also very exciting to see the immense changes from what the 2 floors looked like during our last update! The …Read More


Firewalls, Structural Security, and Build Ups

June 14, 2024

Lindell Masonry has completed the firewall and Bachmann Construction continues to work on structurally securing the building and building the 2nd & 3rd floors back up. The firewall is now complete and with that Lindell Masonry is finished with 210 West Fulton Street for now! Thank you to the Lindell crew for your excellent work. …Read More


2nd & 3rd Floor Progression (Videos)

June 8, 2024

The 210 West Fulton Street Veteran’s Housing Project, when complete, will be an exciting addition to Edgerton, WI. Are you curious about the work that has been completed so far? Edgerton Community Outreach (ECO) has out together 2 videos of the progress that has been completed on the 2nd and 3rd floors of the building! …Read More